Ingangsdatum: 27-04-2001
9.1 A survey report shall be completed for the CAS
survey. The report shall indicate the date, location (place), and where relevant,
whether or not the CAS survey was carried out in dry-dock afloat or at sea. When the
CAS survey is split between different survey stations, a report shall be made for each
portion of the CAS survey.
9.2 Survey
records relating to the CAS survey, including actions taken, shall form an auditable
documentary trail, which shall be made available to the Administration, if requested.
9.3 In addition, the following shall be
included in each CAS survey report:
.1 Extent
of the Survey: .1 identification of the spaces where an overall survey
has been carried out;
.2 identification of location, in
each space, where a close-up survey has been carried out, together with the means of
access used; and
.3 identification of the spaces, and
locations in each space, where thickness measurements have been carried out; and
.2 Results of the Survey: .1 extent and condition of coating in each space.
Identification of spaces fitted with anodes and the overall condition of the anodes;
.2 structural condition reporting for each space, which
shall include information on the following, as applicable:
.1 corrosion (location and type of corrosion such as grooving, pitting, etc.);
.2 cracks (location, description and extent);
.3 buckling (location, description and extent);
.4
indents (location, description and extent); and
.5 areas of
substantial corrosion; and
.3 Actions taken
with respect to findings: .1 details of repairs completed on structural members in
identified spaces, including the repair method and extent; and
.2 list of items to be kept under observation for planning future inspections
and surveys including any thickness measurements.
9.4 Where no defects are found, this shall be stated in the report for each
space.
.5 The narrative report shall be
supplemented by photographs showing the general condition of each space, including
representative photographs or sketches of any of the above reported items.
9.6 The thickness measurement report shall be
verified and endorsed by the attending surveyor.
9.7 The attending surveyors shall sign the CAS survey report.