Onderwerp: Bezoek-historie

1388 UI FSS code chapter 12
Geldigheid:01-01-2012 t/m Status: Geldig vandaag

Dit onderwerp bevat de volgende rubrieken.

Unified interpretation of Chapter 12 of the international Code for Fire Safety Systems

  dd-mm-yyyy = Entry into force
DocumentMSC/Circ.138801-01-2012

 

Ingangsdatum: 01-01-2012

Unified interpretation of Chapter 12 of the international Code for Fire Safety Systems

  dd-mm-yyyy = Entry into force
DocumentMSC/Circ.138801-01-2012

 

Annex

Ingangsdatum: 01-01-2012

Chapter 12, paragraph 2.2.1.3 – Emergency fire pumps in cargo ships

1 It should be documented that chapter 12, paragraph 2.2.1.3, of the Code is satisfied and the suction inlet is fully submerged under all conditions given in this unified interpretation.

1.1 Operational seagoing condition for which roll, pitch and heave should be taken into account.


The lightest seagoing condition should be considered, which is defined as the ballast condition which gives shallowest draught at the position of the sea chest and emergency fire pump as given in the approved stability booklet (or preliminary stability calculation for new building). The following table should be applied for the calculation of roll, pitch and heave. The heave combined pitch and heave combined roll are taken into account separately.

1.1.1 Heave combined pitch1 in head sea

L, m75 and
below
100125150175200225250300350 and
above
, deg4.543.22.72.32.11.81.71.61.5
H, m0.730.80.870.930.981.031.071.111.191.25


Note: Values at the intermediate length of ships are to be obtained by linear interpolation.

where:

L:

length of the ship, in metres, as defined in the International Convention on
Load Lines in force, or length between perpendiculars at the ballast draught,
whichever is greater

 

j:

pitch angle2 as defined in figure 1

 

H:heave amplitude as defined in figure 1.

 

1.1.2 Heave combined roll in beam sea

Heave combined roll angle2 should be taken as:

  1. ships with bilge keels: 11o; and

  2. ships without bilge keels: 13o.

 

Figure 1 – Waterline for which heave combined pitch is taken into account

 

1.2 The emergency fire pump suction should be submerged at the waterlines corresponding to the two following conditions:

  1. a static waterline drawn through the level of 2/3 immersion of the propeller at even keel (for pod or thruster driven ship, special consideration should be given); and

  2. the ship in the arrival ballast condition, as per the approved trim and stability booklet, without cargo and with 10% stores and fuel remaining.

For either condition, roll, pitch and heave need not be applied.

1.3 A ship operating solely in sheltered water issued with SOLAS Certificates should be subject to compliance with the still water submergence requirements set out in paragraph 1.2.1 above.

 

2 In all cases the net positive suction head (NPSH) available for the pump should be greater than the NPSH required.

3 Upon completion of the emergency fire pump installation, a performance test confirming the pump's capacity required in the FSS Code, chapter 12, paragraph 2.2.1.1, should be carried out and, if the emergency fire pump is the main supply of water for any fixed fire-extinguishing system provided to protect the space where the main fire pumps are located, the pump should have the capacity for this system. As far as practicable, the test should be carried out at the draught corresponding to the lightest seagoing condition.


1 The heave combined pitch is taken into account as in figure 1.
2 Angle is to be measured from still waterline and downwards.
Naar boven